TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, DIRECTOR OF PUBLIC WORKS
SUBJECT
title
Euclid Avenue Storm Drain Extension Line "I".
end
RECOMMENDATION
recommendation
1) Establish a new CIP project entitled "Euclid Avenue Storm Drain Extension Line "I" ; 2) appropriate $1,826,845 to the Storm Drain Fund (540) new project SD240, with a corresponding year end transfer from the reserves of the Fund 263 Preserve Storm Drainage Collection System Facilities Development Impact Fee (DIF); 3) award a Professional Services Agreement for $1,706,965 with Proactive Engineering Consultants Inc., Corona, CA for design and bid support services for Project SD240; 4) authorize the fee proposal for expenditures of up to $119,880 for project management services from Z&K Consultants Inc, Riverside, CA; and 5) authorize the City Manager to execute all necessary documents on behalf of the City.
body
FISCAL IMPACT
This new project SD240- Euclid Avenue Storm Drain Extension Line "I" will reduce the 263 Fund Balance of The Preserve Storm Drainage Collection System Facilities Development Impact Fee by $1,826,845. There is sufficient 263 Fund Balance for this project.
CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above further the City's values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:
* Positive City Image
* Financial Stability
* Responsible Long-Range Planning
Revenue:
Expenditure: 5407360 - 48001 | 48003 | 48004 | 48007-SD240
Transfer In: 5407360-50000
Transfer Out: 2631000-40001
BACKGROUND
The City of Chino solicited for professional services for the preparation of Plans, Specifications, and Estimate (PS&E) for the Euclid Avenue Storm Drain Extension-Line I Project.
Storm Drain (SD) Line I is a proposed storm drain facility identified in the Master Plan of Drainage (MPD) for both the cities of Chino and Ontario. SD Line I is located withi...