Legislation Details

File #: 24-185   
Type: New Business Status: Passed
File created: 3/20/2024 In control: City Council
On agenda: 4/2/2024 Final action: 4/2/2024
Title: Construction credit/reimbursement agreement with Chino Development Corporation, a California corporation, and Chino Preserve Development Corporation, a California corporation for the construction of storm drain improvements at various locations in The Preserve.
Attachments: 1. Exhibit A - Storm Drain Atlas Map, 2. Exhibit B - 3.5.24 Lewis Signed Storm Drain DIF Agmt, 3. Exhibit C - Resolution 2024-013
TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, PE, DIRECTOR OF PUBLIC WORKS


SUBJECT
title
Construction credit/reimbursement agreement with Chino Development Corporation, a California corporation, and Chino Preserve Development Corporation, a California corporation for the construction of storm drain improvements at various locations in The Preserve.
end
RECOMMENDATION
recommendation
1) Appropriate $500,000.00 to the Storm Drain Fund with a corresponding year-end transfer in the same amount from The Preserve Storm Drain Development Impact Fee Fund (Fund 263); 2) adopt Resolution 2024-013 memorializing Chino Development Corporation, a California corporation rights to the highest priority reimbursement from The Preserve Storm Drain Development Impact Fee Fund (Fund 263); 3) approve a construction credit/reimbursement agreement with Chino Development Corporation, a California corporation and Chino Preserve Development Corporation, a California corporation for an amount not to exceed $6,485,122.11 for the construction of storm drain improvements at various locations in The Preserve; 4) approve an immediate reimbursement to Chino Development Corporation, a California corporation in the amount of $500,000.00 for said improvements; and 5) authorize the City Manager to execute all the necessary documents on behalf of the City.
body
FISCAL IMPACT
Requires an appropriation of $500,000.00 to the Storm Drain Fund and schedule a corresponding year-end transfer in the same amount from The Preserve Storm Drain Development Impact Fee Fund (Fund 263).
Staff will continue to monitor the fund balance in The Preserve Storm Drain Development Impact Fee program and will make progress payments to the developer (when funds are available) until the terms of the agreement are fulfilled. Each progress payment requires an appropriation of funds and, therefore, each payment will be brought back to the City Council for approval.
CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC...

Click here for full text