Legislation Details

File #: 24-201   
Type: Consent Calendar Status: Passed
File created: 3/28/2024 In control: City Council
On agenda: 6/4/2024 Final action:
Title: Notice of Completion - Street Rehabilitation Project - Pipeline Ave (ST162) and Traffic Signal Modification Project - Grand Avenue at Spectrum East and West (TR171).
Attachments: 1. Notice of Completion - Sequel Contractor, Inc. (ST162 & TR171)
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, PE, DIRECTOR OF PUBLIC WORKS


SUBJECT
title
Notice of Completion - Street Rehabilitation Project - Pipeline Ave (ST162) and Traffic Signal Modification Project - Grand Avenue at Spectrum East and West (TR171).
end
RECOMMENDATION
1) Accept the Street Rehabilitation Project - Pipeline Ave (ST162) and Traffic Signal Modification Project - Grand Avenue at Spectrum East and West (TR171), with Sequel Contractor, Inc., Santa Fe Springs, CA, Contract 2022-062 as complete; 2) authorize the director of Public Works to file the Notice of Completion; and 3) release the retention funds following the 35-day lien period.
body
FISCAL IMPACT
The Project was completed within the Council approved project budget.
CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above further the City's values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:
* Positive City Image
* Financial Stability
* Responsible Long-Range Planning
* Effective Technology







Revenue: Click or tap here to enter text.

Expenditure: 3207100 - 48005 | 48009 - ST162
3207100 - 48005 | 48009 - TR171
3227190 - 48005 | 48009 - ST162
3227190 - 48005 | 48009 - TR171
3277102 - 48005 | 48009 - ST162
Transfer In: Click or tap here to enter text.
Transfer Out: Click or tap here to enter text.
BACKGROUND
On July 6, 2021, the City Council awarded a construction contract to Sequel Contractors, Inc., Santa Fe Springs, CA, for $3,313,079.27 for the Street Rehabilitation Project - Pipeline Avenue ("ST162") and Traffic Signal Modifications - Grand Avenue at Spectrum East and West ("TR171"). Additionally, the City Council authorized expenditures of up to $331,000.00 (10% of the construction contract) for project contingencies, bringing the total construction contract amount not-to-exceed $3,644,079.27. Project ST162...

Click here for full text