Title: Pine Avenue Improvement Amendments.
Attachments: 1. Exhibit A - Pedestrian Improvements, 2. Exhibit B - Pine Agreement Fully Executed, 3. Exhibit C - A1 Fully Executed, 4. Exhibit D - A2 Signed
TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, PE, DIRECTOR OF PUBLIC WORKS


SUBJECT
title
Pine Avenue Improvement Amendments.

end
RECOMMENDATION
recommendation
1) Appropriate $311,439.47 from the unappropriated reserves of the General Fund; 2) schedule a corresponding year-end transfer in the same amount from The Preserve Circulation (Bridges/Signals/Thoroughfares) System Development Impact Fee Fund 260; 3) increase the Capital Improvement Program Budget Project ST203 (1007010 Fund) for Pine Avenue Improvements for Stage 4 in the amount of $311,439.47, for a total Stage 4 project budget not to exceed $3,335,184.47; 4) approve an amendment to the construction credit and reimbursement agreement with Chino Preserve Development Corporation to include additional costs for Pine Avenue Improvements Stage 4 in the amount of $311,439.47 for a total contract not to exceed $17,100,757.47; and 5) authorize the City Manager to execute the necessary documents on behalf of the City.
body
FISCAL IMPACT
Per terms of the agreement, the City is required to make progress payments to the developer for the Falloncrest Right of Way Improvements ("Falloncrest ROW"); West Preserve Loop Rehabilitation ("WPL Rehab"); and the proposed Pedestrian Improvements ("Ped Improvements"). The funding allocations are summarized below:
Project ST203 - Pine Avenue Improvements Stage 4:

CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above further the City's values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:
* Positive City Image

Revenue:

Expenditure: 1007010-40010-ST203
Transfer In: 1001000-50000
Transfer Out: 2601000-40001

BACKGROUND
Pine Avenue, between Euclid and Hellman Avenues, is a major roadway arterial within The Preserve Specific Plan area that will be a total of six-lanes with a raised landscaped median when fully constructed. The phased construction o...