TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, PE, DIRECTOR OF PUBLIC WORKS
SUBJECT
title
Final Acceptance of Public Improvements Calvary Chapel Chino Hills Project 4201 Eucalyptus Avenue (M22-0001).
end
RECOMMENDATION
1) Accept public improvements as complete for project M22-0001; 2) authorize release of the performance bond and initiate the warranty bond; and 3) authorize the City Manager to execute the necessary documents on behalf of the City.
body
FISCAL IMPACT
There are sufficient funds included in the City's Operating Budget to support the ongoing maintenance activities related to the public improvements being accepted.
CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above furthers the City's values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:
* Positive City Image
* Public Service Excellence through Internal and External Partnerships
Revenue: Click or tap here to enter text.
Expenditure:
Transfer In: Click or tap here to enter text.
Transfer Out: Click or tap here to enter text.
BACKGROUND
Calvary Chapel Chino Hills Foundation, located at 4201 Eucalyptus Avenue (see Exhibit A), proposed to build a new accessible pedestrian sidewalk on the north side of Eucalyptus Avenue. The sidewalk was intended to extend from Appian Way to approximately 517 feet east of the intersection. This project aimed to improve pedestrian access to the church from a nearby industrial property, which has been used frequently as an overflow parking lot by parishioners.
In December 2022, the Development Services Department approved an Engineering Cost Estimate provided by Calvary Chapel for the design and construction of the sidewalk. The City also required the installation of traffic interconnect conduit and pull box improvements on Eucalyptus Avenue be made alongside the sidewalk installation to enable the future extension of the existing fib...
Click here for full text