Amendment to Measure I Capital Improvement Plan for Fiscal Years 2024-2028.
end
RECOMMENDATION
Adopt Resolution No. 2024-027 to amend Resolution No. 2023-067 revising the Measure I Capital Improvement Plan for Fiscal Year 2024-2028.
body
FISCAL IMPACT
Projects identified on the Measure I Five Year Plan are funded with restricted Measure I revenues and are included in the City’s Capital Improvement Program.
CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above further the City’s values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:
• Responsible Long-Range Planning
|
Revenue: Click or tap here to enter text. |
Expenditure: |
|
Transfer In: Click or tap here to enter text. |
Transfer Out: Click or tap here to enter text. |
BACKGROUND
Measure I, the San Bernardino County Transportation Sales Tax Program, requires that each local jurisdiction receiving annual program revenues adopt, by resolution, a Five-Year Capital Improvement Plan. The Capital Improvement Plan lists specific projects where Measure I Funds will be used. The Five-Year Measure I Capital Improvement Plan was adopted by Resolution No. 2023-067 on November 7, 2023, for Fiscal Years 2024-2028.
ISSUES/ANALYSIS
The Fiscal Year 2023-2024 Capital Improvement budget allocated Measure I funding for two projects. Below is a summary of the projects and adjustments.
• Coordinated Traffic Signal System (N7604)
Funding initially designated for Project N7604 has been reassigned to the Traffic Signal Synchronization Project (MS236), facilitating synchronization of traffic signals citywide.
• Preserve/College Park Slurry Project (MS222)
MS222 will be removed from the list as the Citywide Slurry Maintenance FY24 Project (NC241), encompasses both Preserve and College Park locations, therefore project MS222 will no longer be necessary.
• Traffic Signal Installation - Eucalyptus at Fern Avenue (TR240)
Measure I funding will be used to supplement the pavement rehabilitation portion of the project.
These adjustments ensure compliance with the San Bernardino County Transportation Sales Tax Program requirements. Consequently, the City Council is required to approve an updated Fiscal Year 2023-2024 Measure I Capital Improvement Plan projects list. Resolution No. 2024-027 outlines the revised Measure I Capital Improvement Plan for Fiscal Year 2023-2024.