City of Chino Header
File #: 24-630   
Type: Consent Calendar Status: Passed
File created: 11/27/2024 In control: City Council
On agenda: 12/17/2024 Final action: 12/17/2024
Title: Amendment No. 1 with HR Green Pacific, Inc. for the Community Development Block Grant (CDBG) Program Alley Improvement Project FY 23-24 (SN240).
Attachments: 1. Exhibit A - Project Location Map, 2. Exhibit B - PSA Amendment No. 1

TO:                                           LINDA REICH, CITY MANAGER

FROM:                      HYE JIN LEE, PUBLIC WORKS DIRECTOR

 

 

SUBJECT

title

Amendment No. 1 with HR Green Pacific, Inc. for the Community Development Block Grant (CDBG) Program Alley Improvement Project FY 23-24 (SN240).

end

RECOMMENDATION

Approve Amendment No. 1 for $3,800 with HR Green Pacific, Inc., (Contract No. 2025-076) for the Community Development Block Grant (CDBG) Program Alley Improvement Project FY 23-24 (SN240) for a revised total contract amount not to exceed $52,657.10; and authorize the City Manager to execute all necessary documents on behalf of the City.

body

FISCAL IMPACT

Sufficient funds are budgeted in the Fiscal Year 2024-25 Capital Improvement Program (CIP) for the Community Development Block Grant (CDBG) Program Alley Improvement Project (SN240).

TOTAL PROJECT BUDGET - SN240

Funding Source

Adopted Budget

Additional Appropriation

Revised Project Budget

Fund 350 - CDBG

$219,256.00

$0

$219,256.00

 

CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES

The recommendation detailed above further the City’s values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:

                     Positive City Image

                     Responsible Long-Range Planning

 

Revenue: Click or tap here to enter text. 

Expenditure: 3508030 - 48004 - SN240

Transfer In: Click or tap here to enter text.

Transfer Out: Click or tap here to enter text.

BACKGROUND

The Community Development Block Grant (CDBG) Program Alley Improvement Project (SN240) will occur in the east-west alley between D Street and Chino Avenue from 3rd Street to 5th Street.  The scope of work generally includes pavement reconstruction of the alley. The City’s intention is to have the alley resurfaced by completely removing the existing pavement and replacing with subgrade and new asphalt.  Reconstruction of the alley will also improve the drainage in the area.

ISSUES/ANALYSIS

On May 10, 2024, the City released an informal request for Proposals (RFP) from the on-call consultant list (RFP#2023-3003) for design services, following the City procurement policy. The City received (3) three proposals by the closing date. Staff evaluated and ranked the proposals based on the following weighted criteria:

                     Experience/Qualifications: 20%

                     Past Performance/References: 20%

                     Plan Methodology/Project Approach: 30%

                     Quality of Responsiveness of Proposal: 15%

                     Cost Evaluation: 15%

 

HR Green Pacific, Inc. was selected as the highest-ranking proposal by the evaluation committee. On July 29, 2024, an agreement for $48,840 was processed administratively as the agreement amount was within the City Manager’s approval range.

Additional costs are required to include the design of (4) four alley approaches to comply with the City’s Policy on Accessible Facilities in the Public Right-of-Way. The cost breakdown to include the necessary design is as follows:

Item

Amount

Survey and Design of (4) four alley approaches

$3,800.00

Total:

$3,800.00

 

Staff recommends the City Council approve Amendment No. 1 for $3,800 with HR Green Pacific, Inc. (Contract No. 2025-076) for additional design services for the CDBG Program Alley Improvement Project (SN240) for a revised total contract amount not to exceed $52,657.10.

 

Attachments: Exhibit A - Project Location Map

Exhibit B - Contract Amendment No. 1