Legislation Details

File #: 26-401   
Type: Consent Calendar Status: Passed
File created: 6/29/2026 In control: City Council
On agenda: 7/21/2026 Final action: 7/21/2026
Title: Award a Professional Services Agreement to Glenn Lukos Associates, Inc. for the College Park Magnolia Channel Biological Monitoring and Reporting Services.
Attachments: 1. Professional Services Agreement - Glenn Lukos Associates, Inc.

TO:                      LINDA REICH, CITY MANAGER

FROM:                      HYE JIN LEE, PE, DIRECTOR OF PUBLIC WORKS

 

 

SUBJECT

title

Award a Professional Services Agreement to Glenn Lukos Associates, Inc. for the College Park Magnolia Channel Biological Monitoring and Reporting Services.

end

RECOMMENDATION

Award a Professional Services Agreement for $196,260 to Glenn Lukos Associates, Inc., Santa Ana, CA for a five-year term for Magnolia Channel Biological Monitoring and Reporting Services; and authorize the City Manager to execute all necessary documents on behalf of the City.

body

FISCAL IMPACT

Sufficient funds have been included in the FY2026-27 Adopted Budget in the Storm Drain Fund (Fund 540). Sufficient funds will be budgeted in future proposed Fiscal Year Operating Budgets.

Fund 540 Annual Expenditures Per Fiscal Year

FY2026-2027

$36,150

FY2027-2028

$36,150

FY2028-2029*

$44,600*

FY2029-2030

$39,680

FY2030-2031

$39,680

Total Expenditures

$196,260

*Note: The contract cost is higher for FY 2028-2029 due to reporting requirements from the California Department of Fish and Wildlife.

CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES

The recommendation detailed above further the City’s values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:

                     Positive City Image

                     Financial Stability

                     Responsible Long-Range Planning

 

 

 

Revenue: Click or tap here to enter text. 

Expenditure: 5407350-43650

Transfer In: Click or tap here to enter text.

Transfer Out: Click or tap here to enter text.

BACKGROUND

As a part of the College Park Development’s conditions of approval, off-site improvements alongside Edison Avenue impacted existing off-site drainage facilities, including the Magnolia Channel, requiring mitigation measures to address those impacts. The Magnolia Channel, located between Satterfield Way and Appalachian Street, is a man-made, earthen drainage channel that receives stormwater flows from the City's storm drain system and ultimately conveys water to the Santa Ana River.  The California Department of Fish and Wildlife required the creation of native habitat including freshwater marsh and grassland within and adjacent to the Magnolia Channel.

 

Since the City's acceptance of the required public improvements, the City of Chino has been responsible for the ongoing operation and maintenance of the Magnolia Channel. Routine maintenance is necessary to preserve the channel's hydraulic capacity, facilitate the continuous conveyance of stormwater, minimize standing water, and reduce conditions that may contribute to mosquito breeding.  Maintenance activities include vegetation management, sediment and debris removal, and invasive species control.

 

To perform these activities, the City operates under Streambed Alteration Agreement No. 1600-2020-0096-R6 with the California Department of Fish and Wildlife (CDFW), which is effective through July 9, 2032. The agreement establishes measures to protect fish and wildlife resources and requires the City to conduct biological monitoring and reporting services associated with maintenance activities. These requirements include pre-maintenance nesting bird surveys, nesting bird monitoring and reporting, annual maintenance reports, and long-term status reports submitted to CDFW.

 

Since the execution of the Streambed Alteration Agreement with the CDFW in 2020, Glenn Lukos Associates, Inc. has provided the biological monitoring, environmental compliance, and reporting services necessary to support the City's obligations under the Agreement. These services have enabled the City to perform routine maintenance activities within Magnolia Channel while maintaining compliance with California Department of Fish and Wildlife requirements.

 

ISSUES/ANALYSIS

Glenn Lukos Associates, Inc. has provided the biological monitoring and reporting services required under the City’s Streambed Alteration Agreement and possesses extensive knowledge of the Magnolia Channel mitigation site, permit requirements, historical monitoring activities, and reporting obligations. Annual maintenance reports and long-term status reports required by the California Department of Fish and Wildlife are based on data and observations collected over multiple years. As a result, transitioning these services to another consultant would require significant time for project familiarization, review of historical monitoring records, and coordination with regulatory agencies.

 

Continuing services with Glenn Lukos Associates, Inc. ensures consistency in monitoring methodologies, reporting, and regulatory compliance while minimizing the potential for delays or disruptions to the City's maintenance activities. In accordance with Chapter 3.32 of the Chino Municipal Code, staff is recommending a noncompetitive procurement for these specialized professional services to provide continuity of operations and support the City's ability to efficiently meet its obligations under the Streambed Alteration Agreement.

Staff recommends that the City Council award a Professional Service Agreement with Glenn Lukos Associates, Inc. in the amount of $196,260 for a five-year term for Magnolia Channel Biological Monitoring and Reporting Services.

 

Attachments: Professional Services Agreement - Glenn Lukos Associates, Inc.