File #: 25-405   
Type: Consent Calendar Status: Passed
File created: 8/19/2025 In control: City Council
On agenda: 9/16/2025 Final action: 9/16/2025
Title: Professional Service Agreement - Southstar Engineering and Consulting, Inc. for Civil Engineering Design Services for the Sewer Line Rehabilitation Fiscal Year 2026 Project (SW260).
Attachments: 1. Exhibit A - SW260 Vicinity Map, 2. Exhibit B - PSA Southstar

TO:                      LINDA REICH, CITY MANAGER

FROM:                      HYE JIN LEE, PE, DIRECTOR OF PUBLIC WORKS

 

 

SUBJECT

title

Professional Service Agreement - Southstar Engineering and Consulting, Inc. for Civil Engineering Design Services for the Sewer Line Rehabilitation Fiscal Year 2026 Project (SW260).

end

RECOMMENDATION

Award a Professional Service Agreement to Southstar Engineering and Consulting, Inc. for Civil Engineering Design Services for the Sewer Line Rehabilitation Fiscal Year 2026 Project (SW260) for $363,990; and authorize the City Manager to execute all necessary documents on behalf of the City.

body

FISCAL IMPACT

Sufficient funds are budgeted in the Fiscal Year 2025-26 Capital Improvement Program (CIP) for the Sewer Line Rehabilitation Fiscal Year 2026 Project (SW260).

 

Sewer Line Rehabilitation Fiscal Year 2026 (SW260)

Fund

Adopted Budget

Expenditures

Budget Available

530 - Sewer Fund

$2,000,000

$0

$2,000,000

 

CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES

The recommendation detailed above furthers the City’s values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:

                     Superior Customer Service

                     Financial Stability

                     Responsible Long-Range Planning

 

 

 

 

 

 

 

Revenue: Click or tap here to enter text.

 

Expenditure: 5307340 – 48004 - SW260

Transfer In: Click or tap here to enter text.

Transfer Out: Click or tap here to enter text.

BACKGROUND

The City of Chino encompasses approximately 31 square miles and provides wastewater collection services to 21,000 sewer connections through approximately 270 miles of sanitary sewer pipelines. Staff developed a Capital Improvement Program that identifies recommended sewer line replacement projects and recommended phasing of the replacement projects to ensure the City efficiently collects and conveys wastewater for treatment for its customers. The selection and phasing of projects considers the age of the pipe, material, the number of recent repairs, and potential for a sewer overflow.

The project scope includes pipeline segments identified for replacement in the 2022 Sewer Master Plan, as well as segments selected by staff based on maintenance and repair history. The locations listed below are also referenced in Exhibit A - Vicinity Map:

NO.

LOCATION

LINEAR FEET

1.

Kellogg Avenue - Sutter Street to the cul-de-sac

368

2.

Monte Vista Avenue - near the intersection of Lincoln Avenue

240

3.

6th Street Alley - East of 6th Street, from B Street to the alley south of B Street

280

4.

Durango Street - Arvidson Road to Noble Place

399

5.

Clover Street - Joshua Place to Bunker Hill Place

455

6.

Amber Road - Carter Street to approximately 360 feet south of Carter Street

383

7.

Central Avenue - Edison Avenue to Anderson Street

1,800

8.

Anderson Street - Central Avenue to Redwood Street

680

Total Length of Sewer Main Line Replacement  

4,605

 

The project will replace approximately 4,605 linear feet of existing 8-inch and 10-inch sewer mains constructed of either non-reinforced concrete pipe (CP) or vitrified clay pipe (VCP) depending on the location throughout the City.

The design scope includes topographical survey, utility research/coordination, potholing, preparing plans, specifications, cost estimates and bid/construction support. Moreover, this capital improvement will reduce potential for sewer overflows, more costly repairs in the future, decrease wastewater infiltration, and improve the overall system operations. Public Works service operations will be improved by adding cleanout access points at every sewer lateral connection at the property line to improve sewer lateral services to the properties.

ISSUES/ANALYSIS

On August 4, 2025, Public Works staff solicited an Informal Request for Proposals (RFP) from the Master On-Call consultant list (RFP No. 2023-3003) to three (3) firms for Civil Engineering Professional Services. The City received two (2) proposals by the closing date of August 15, 2025. The proposals were evaluated and ranked based on the following criteria:

                     Experience/Qualifications

                     Past Performance/References

                     Plan Methodology/Project Approach

                     Quality and Responsiveness of Proposal

                     Cost Evaluation

 

Following evaluation, Southstar Engineering and Consulting, Inc. received the highest score and is recommended for the contract award.

Evaluation Results:

RANK

CONSULTANT

LOCATION

1.

Southstar Engineering and Consulting, Inc.

Riverside, CA

2.

EXP

San Bernardino, CA

*N/A

David Beckwith and Associates, Inc

Rancho Cucamonga, CA

                     * Declined to submit proposal

Staff requests City Council approval to award a contract to Southstar Engineering and Consulting, Inc.  for Civil Engineering Services, for a not-to-exceed amount of $363,990.

 

Attachment: Exhibit A – Vicinity Map

Exhibit B – PSA Southstar Engineering and Consulting, Inc.