Title: Notice of Completion - Monte Vista Park Improvement Project - PK183.
Attachments: 1. Notice of Completion - Los Angeles Engineering, Inc. (PK183), 2. PK183 - May 2022, 3. PK183 - November 2023
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                      LINDA REICH, CITY MANAGER

FROM:                      HYE JIN LEE, DIRECTOR OF PUBLIC WORKS

 

 

SUBJECT

title

Notice of Completion - Monte Vista Park Improvement Project - PK183.

end

RECOMMENDATION

1) Accept the Monte Vista Park Improvement Project (PK183), with Los Angeles Engineering Inc., Covina, CA, Contract No. 2023-156, as complete; 2) authorize the Director of Public Works to file the Notice of Completion; and 3) authorize the release of the retention funds following the 35-day lien period.

body

FISCAL IMPACT

The project was completed within the City Council approved budget.

 

CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES

The recommendation detailed above further the City’s values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:

•                     Positive City Image

•                     Responsible Long-Range Planning

 

 

 

 

 

 

 

Revenue: Click or tap here to enter text. 

Expenditure: 3207100 - 48005 | 48009   3408300 - 48005 | 48009   3508030 - 48005 | 48009   6102050 - 48005

Transfer In: Click or tap here to enter text.

Transfer Out: Click or tap here to enter text.

BACKGROUND

On October 18, 2022, City Council awarded a construction contract to Los Angeles Engineering, Inc., Covina, CA in the amount of $1,282,500 for the Monte Vista Park Improvement Project (PK183). Additionally, the City Council authorized expenditures of up to $128,250 for project contingencies, bringing the construction contract budget to an amount not-to-exceed $1,410,750. 

All the park improvements have been constructed. The location of the street improvements constructed as a part of this project are as listed below:

•                     Intersection of Monte Vista and D Street

ISSUES/ANALYSIS

All work has been completed per the terms of the construction contract 2023-156. The scope of work included accessible pedestrian improvements to the intersection of Monte Vista Avenue at D Street. New bulb-out ramps now cross Monte Vista Avenue with a new advanced pedestrian-activated flashing beacon system. Fiber optic communication was also installed from City Hall to Monte Vista Park, the Neighborhood Activity Center, and the Chino Youth Museum. The completed work improves pedestrian accessibility and safety and enhances technology connectivity to these city Facilities. The following is a summary of the final accounting of costs for construction:

 

Project PK 183

Contract

Contingency

Original Contract & Contingency

$1,282,500.00

$128,250.00

Change Order No. 1

($33,134.42)

 

Change Order No. 2

$43,731.00

($43,731.00)

Change Order No. 3

$47,137.00

($47,137.00)

Final Contract & Contingency

$1,340,233.58

$37,382.00

 

Los Angeles Engineering, Inc., Covina, CA, has complied with the terms of the contract.  A Notice of Completion has been prepared for filing with the San Bernardino County Recorder's Office.  The retention funds will be released following the 35-day lien period.

 

Attachment:                      Notice of Completion - Los Angeles Engineering, Inc. (PK 183)