File #: 25-552   
Type: Consent Calendar Status: Passed
File created: 11/17/2025 In control: City Council
On agenda: 1/20/2026 Final action: 1/20/2026
Title: ???Notice of Completion for the Traffic Signal Installation - Eucalyptus Avenue at Fern Avenue Project (TR240) with Elecnor Belco Electric, Inc.??
Attachments: 1. Exhibit A - Project Vicinity Map TR240, 2. Exhibit B_Notice of Completion (Belco)

TO:                      LINDA REICH, CITY MANAGER

FROM:                      HYE JIN LEE, PE, DIRECTOR OF PUBLIC WORKS

 

 

SUBJECT

title

​​​Notice of Completion for the Traffic Signal Installation - Eucalyptus Avenue at Fern Avenue Project (TR240) with Elecnor Belco Electric, Inc.​​

end

RECOMMENDATION

​​​1) Accept the Contract No. 2024-263 to Elecnor Belco Electric as complete for the Traffic Signal Installation - Eucalyptus Avenue at Fern Avenue Project (TR240); 2) authorize the Director of Public Works to file the Notice of Completion on behalf of the City of Chino; and 3) authorize the release of retention funds following the 35-day lien period.​​

body

FISCAL IMPACT

​​​The contract was completed within the City Council approved contract budget for TR240. There is an unused contingency balance of $68,502.44 which will be returned to the General Fund Balance at our year end close.​​

TR240 - Traffic Signal Installation - Eucalyptus Avenue at Fern Avenue

​Contract

​Contingency

​Original Contract & Contingency

​$1,146,360.00

​$114,636.00

​Contract Change Order No. 1

​$18,831.45

​($18,831.45)

​Contract Change Order No. 2

​$27,302.11

​-($27,302.11)

​Contract Change Order No. 3

​($14,510.10)

$0.00

​Final Contract Amount & Contingency

​$1,177,983.46

​$68,502.44

 

CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES

The recommendation detailed above furthers the City’s values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:

                     Positive City Image

                     Responsible Long-Range Planning

                     Public Service Excellence through Internal and External Partnerships

 

 

 

 

 

 

 

Revenue: Click or tap here to enter text. 

Expenditure: 3207100 - 48009 - TR240

Transfer In: 1001000-40001

Transfer Out: 3201000-50000

BACKGROUND

​On May 7, 2024, the City Council awarded a construction contract to Elecnor Belco Electric, Inc., for the Traffic Signal Installation - Eucalyptus Avenue at Fern Avenue Project (TR240) for $1,146,360 and a contingency amount of $114,636. On March 6, 2025, the traffic signal was activated and is now fully operational. On April 15, 2025, the City Council approved a funding modification, applying the developer’s (Lennar) contribution to the project budget, which reduced the committed Development Impact Fees by the same amount. The project scope of work included construction of a new traffic signal, fiber optic interconnect, a new traffic camera, ADA compliant curb ramps, and completion of landscape and hardscape on the north-east corner of the intersection. Additionally, the pavement leading up to the intersection was rehabilitated as depicted in Exhibit A.

In addition, outside the project scope, the ADA Coordinator, Public Works Inspector, Public Works Services Manager, and Project Engineer conducted an inspection of existing pedestrian improvements within the City’s right-of-way. Accessibility deficiencies identified during the inspection were addressed by Public Works Services staff, with repairs funded by the developer’s accessibility remediation contributions. The intersection is now fully accessible to pedestrians of all abilities.

ISSUES/ANALYSIS

​​​All work has been completed per the terms of the original construction contract and approved change orders. Change Orders No. 1 and 2 were approved by staff within the authorized contingency balance and included added pavement-related work; landscape work and tree replacement; and extension of the equestrian trail along the north side of Eucalyptus Avenue east of Fern Avenue. Change Order No. 3 is the final balancing change order addressing changes in quantities to reflect actual work performed.

 

Elecnor Belco Electric, Inc. has complied with the terms of the contract. A Notice of Completion has been prepared for filing with the San Bernardino County Recorder’s Office. The retention funds will be released following a 35-day lien period.

 

Attachments:                     Exhibit A - Project Vicinity Map (TR240)

​Exhibit B - Notice of Completion (Elecnor Belco Electric, Inc.)