TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, PE, DIRECTOR OF PUBLIC WORKS
SUBJECT
title
Traffic Signal Installation at Eucalyptus & Fern (TR240).
end
RECOMMENDATION
recommendation
1) Appropriate $175,000 from the unappropriated reserves of the Measure I Fund with a corresponding increase to the Traffic Signal Installation at Eucalyptus & Fern (TR240); 2) appropriate $546,402 to the Transportation Fund with a corresponding backfill transfer from the Bridges/Signal/Thoroughfare Fund 220, bringing the total project TR240 budget to $1,271,402; 3) award a construction contract to Elecnor Belco Electric, Inc., Chino, CA, for the Traffic Signal Installation at Eucalyptus & Fern (TR240) for a contract amount of $1,146,360 and authorize up to $114,636 (10% of the contract amount) for construction contingencies for a not to exceed contract amount of up to $1,260,996; and 4) authorize the City Manager to execute all necessary documents on behalf of the City.
body
FISCAL IMPACT
The fiscal impact of awarding the contract listed above for Project TR240 will reduce the reserves of the Measure I Fund 322 balance by $175,000, and Fund 220 Bridges/Signal/Thoroughfare by $546,402. The City received a $553,500 in-lieu fee from Lennar Homes (Developer) for the University Park Community development, which was appropriated to Project TR240. Due to bids coming in higher than expected, an additional $175,000 from Measure I and $546,402 from the Bridges/Signal/Thoroughfare is needed to complete the project. There is sufficient fund balance in both Fund 322 and Fund 220 for this purpose.
CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above further the City's values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:
* Positive City Image
* Responsible Long-Range Planning
* Effective Technology
Revenue: 3201000-50000
Expenditure: 3207100 - 40010|48005|...