TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, PUBLIC WORKS DIRECTOR
SUBJECT
title
Amendment No. 1 with HR Green Pacific, Inc. for the Community Development Block Grant (CDBG) Program Alley Improvement Project FY 23-24 (SN240).
end
RECOMMENDATION
Approve Amendment No. 1 for $3,800 with HR Green Pacific, Inc., (Contract No. 2025-076) for the Community Development Block Grant (CDBG) Program Alley Improvement Project FY 23-24 (SN240) for a revised total contract amount not to exceed $52,657.10; and authorize the City Manager to execute all necessary documents on behalf of the City.
body
FISCAL IMPACT
Sufficient funds are budgeted in the Fiscal Year 2024-25 Capital Improvement Program (CIP) for the Community Development Block Grant (CDBG) Program Alley Improvement Project (SN240).
TOTAL PROJECT BUDGET - SN240
Funding Source
Adopted Budget
Additional Appropriation
Revised Project Budget
Fund 350 - CDBG
$219,256.00
$0
$219,256.00
CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above further the City's values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:
* Positive City Image
* Responsible Long-Range Planning
Revenue: Click or tap here to enter text.
Expenditure: 3508030 - 48004 - SN240
Transfer In: Click or tap here to enter text.
Transfer Out: Click or tap here to enter text.
BACKGROUND
The Community Development Block Grant (CDBG) Program Alley Improvement Project (SN240) will occur in the east-west alley between D Street and Chino Avenue from 3rd Street to 5th Street. The scope of work generally includes pavement reconstruction of the alley. The City's intention is to have the alley resurfaced by completely removing the existing pavement and replacing with subgrade and new asphalt. Reconstruction of the alley will also improve the drainage in the area.
ISSUES/ANALYSIS
On May 10, 2024, the City released an informal request for Propo...