TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, DIRECTOR OF PUBLIC WORKS
SUBJECT
title
Intersection Improvements (Moonspinner Street and West Preserve Loop).
end
RECOMMENDATION
recommendation
Approve the plans and specifications for construction as approved by the Director of Public Works and authorize the solicitation of construction bids for TR271 - Intersection Improvements at (Moonspinner Street at West Preserve Loop).
body
FISCAL IMPACT
Funds are currently budgeted in the Fiscal Year 2026-27 Capital Improvement Program (CIP) for this project. Funding was identified from two funding sources, Measure I transportation improvement funds and General Fund. The adopted Fiscal Year 2026-27 project budget is summarized below:
TR271 - Intersection Improvements (Moonspinner Street at West Preserve Loop)
Funding Source
Appropriation
Measure I - Fund 322
$100,000
General Fund - Fund 100
$50,000
*Total Budget:
$150,000
*Total reflects estimated construction costs only; staff will request additional funding once bids are received and project is ready for award.
CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above further the City’s values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:
? Positive City Image
? Superior Customer Service
Revenue:
Expenditure: TR271
Transfer In: Transfer Out:
BACKGROUND
The TriPointe Homes residential development located at the northeast corner of Pine Avenue and West Preserve Loop began construction of public improvements in mid-2025. One of the developer's conditions of approval was to construct the ultimate street improvements along their frontage on West Preserve Loop. That work included widening the roadway on the east side and establishing a raised median identified in the Preserve Specific Plan. After constructing the median, but before finishing the final pavement resu...