City of Chino Header
File #: 25-158   
Type: Consent Calendar Status: Passed
File created: 3/25/2025 In control: City Council
On agenda: 4/15/2025 Final action: 4/15/2025
Title: Traffic Signal Installation - Eucalyptus Avenue at Fern Avenue Project (TR240).
Attachments: 1. TR240 Location Map
TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, PE, DIRECTOR OF PUBLIC WORKS


SUBJECT
title
Traffic Signal Installation - Eucalyptus Avenue at Fern Avenue Project (TR240).
end
RECOMMENDATION
1) Appropriate $609,291 from the Transportation Fund Balance 320 for the Traffic Signal Installation - Eucalyptus Avenue at Fern Avenue Project (TR240); 2) reduce the project budget by $609,291 from the Bridges/Signals/Thoroughfare (220) Development Impact Fee fund.; and 3) authorize the City Manager to execute all necessary documents on behalf of the City.
body
FISCAL IMPACT
There is no change in the total project budget. The appropriation of $609,291 will come from the available Transportation Fund Balance, which had previously received a developer fair share contribution of $553,500 and the remaining accessibility remediation settlement agreement of $55,791 for this project, account 3201000-59358. This appropriation will also result in an increase to the Fund 220 fund balance by $609,291 due to the removal of its budget. The total project budget will remain at $1,272,029.01.
TR240 Project Budget
Funding Source
Adopted Budget
Additional Appropriation
Reducing Project Budget
Total
220 - Bridges/Signals/Thoroughfare
$1,097,029.01
$ 0.00
($609,291.00)
$487,738.01
322 - Measure I
$175,000.00
$ 0.00
$ 0.00
$175,000.00
320 - Transportation
$ 0.00
$609,291.00
$ 0.00
$609,291.00
Totals:
$1,272,029.01
$609,291.00
($609,291.00)
$1,272,029.01

CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above further the City's values and strategic issues that serve as key pillars on which identified priorities, goals, and action plans are built, by fostering:
* Financial Stability
* Responsible Long-Range Planning


Revenue: Click or tap here to enter text.

Expenditure:
Transfer In: 3201000 - 59358
Transfer Out: 3207100 - 40005 - TR240
BACKGROUND
On May 7, 2024, the City Council awarded a construction contract to Elecnor Belco Electric, Inc., f...

Click here for full text