Title: Approve Amendment No. 3 with Proactive Engineering Consultants, dba Q3 Consulting for Euclid Avenue Storm Drain Extension Line I (SD240).
Attachments: 1. Exhibit A - Line "I", Line "H" and Pine Ave Widening Scope Limits Map, 2. Exhibit B - Amendment No. 3 - Q3
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: LINDA REICH, CITY MANAGER
FROM: HYE JIN LEE, DIRECTOR OF PUBLIC WORKS


SUBJECT
title
Approve Amendment No. 3 with Proactive Engineering Consultants, dba Q3 Consulting for Euclid Avenue Storm Drain Extension Line I (SD240).
end
RECOMMENDATION
recommendation
(1) Approve Contract Amendment No. 3 with Proactive Engineering Consultants, dba Q3 Consulting, Contract No. 2024-206 for $767,870.76 for additional design engineering and environmental services related to Project SD240; (2) Approve an increase to the Capital Improvement Program (CIP) budget for Euclid Avenue Storm Drain Extension Line I – Project SD240 in the amount of $687,806.78 for a total project budget not to exceed $2,564,651.78. (3) Approve a budget transfer in the amount of $687,806.78 from the Preserve Storm Drainage Collection System Facilities Development Impact Fee (Fund 263) to the Storm Drain Capital Fund (Fund 540). (4) Rename project SD240 – Euclid Ave Storm Drain Extension Line I to “Euclid Ave Storm Drain Extension Line I and Pine Ave Storm Drain Extension Line H”; and (5) Authorize the City Manager to execute all necessary documents on behalf of the City.

body
FISCAL IMPACT
This action will require a budget transfer of $687,806.78 from the Preserve Storm Drainage Collection System Facilities Development Impact Fee (DIF) Fund (263) to the Storm Drain Capital Fund (540). The FY 2026-27 project budget is summarized below:
Project SD240 – Euclid Ave Storm Drain Extension Line I and Pine Ave
Storm Drain Extension Line H Fund Adopted Budget
Expenditures/ Encumbrances
Appropriation
Available Budget

540 – Storm Drain
$1,876,845
$1,746,781.02
-
$130,063.98

263 – Preserve Storm Drainage Collection System DIF
-
-
$687,806.78
$687,806.78

*Total Available Project Budget
$817,870.76

?*Total project budget reflects design costs only.
CITY OF CHINO MISSION / VISION / VALUES / STRATEGIC ISSUES
The recommendation detailed above further the City’s values and strategic...